Question ID 10869 | You work as a Project Manager at ABC.com. You are using Microsoft Project Professional 2010 to |
Option A | You should consider applying a Late Tasks filter to the Gantt chart view. |
Option B | You should consider double clicking the task to view the task information. |
Option C | You should consider selecting View > More Views > Task Details Form to view the task details. |
Option D | You should consider selecting Inspect Task on the Tasks tab. |
Correct Answer | C |
Question ID 10870 | You work as a Project Manager at ABC.com. You are using Microsoft Project Professional 2010 to |
Option A | The duration of the Software Coding task has taken 8 days more than forecast. |
Option B | The duration of the Software Coding task has taken 8 days less than forecast. |
Option C | The Software Coding task was completed 8 days later than forecast. |
Option D | The Software Coding task was completed 8 days earlier than forecast. |
Correct Answer | B |