Question ID 10863

Your work at ABC.com includes management of projects using Microsoft Project Professional
2010.
You are configuring the tasks for a new project. You notice that the default constraint type for
tasks that you create is set to As Soon As Possible. You are required to make sure that the default
constraint type for new tasks is changed to As Late As Possible
Which of the following actions should you take?

Option A

You should configure the Schedule From option in the Project Information window to Project
Finish Date.

Option B

You should configure the Schedule From option in the Project Information window to Project
Start Date.

Option C

You should check the New Tasks are effort driven check box in the Project Options.

Option D

You should select all tasks then click the Update Project option.

Correct Answer A
Explanation


Question ID 10864

You work as a Project Manager at ABC.com. You are using Microsoft Office Project Professional
2010 to manage a project.
Task1 is represented by the following icon in the default Gantt Chart view:Task2 is represented by the following icon in the default Gantt Chart view:
What would you need to change to configure Task2 to be the same type as Task1?

Option A

You would need to configure Task2 to be automatically scheduled.

Option B

You would need to configure Task2 to be manually scheduled.

Option C

You would need to configure Task2 as critical.

Option D

You would need to configure Task2 as a milestone.

Correct Answer B
Explanation