Question ID 10865

Your work at ABC.com includes management of projects using Microsoft Project Professional
2010.
You are calculating the timescales for a new project using the bottom-up scheduling method. You
have created three tasks named Drawings, Prototype and Review.
You want to group the Drawings, Prototype and Review tasks into a project phase named Design.
How would you group the three tasks?

Option A

By selecting the three tasks and clicking the Outdent Task option.

Option B

By selecting the row above the three tasks and entering a new Summary Task.

Option C

By selecting the three tasks and clicking the Indent Task option.

Option D

By selecting the three tasks and selecting the Insert Summary Task option.

Correct Answer D
Explanation


Question ID 10866

Your work at ABC.com includes management of projects using Microsoft Project Professional
2010.How can you display a task that lists the project name, total project duration and start and finish
dates by default in the project schedule?

Option A

By navigating to the Format tab and selecting the Critical Tasks checkbox.

Option B

By navigating to the Format tab and selecting the Summary Tasks checkbox.

Option C

By navigating to the Format tab and selecting the Project Summary Task checkbox.

Option D

By navigating to the Format tab and selecting the Outline Number checkbox.

Correct Answer C
Explanation