Question ID 10861

You work as a Project Manager at ABC.com. You are using Microsoft Project Professional 2010 to
manage a new project.
The project will be divided into five major phases. The time that each phase will take is still being
calculated but the entire project needs to be completed within 6 months.
How should you configure the project to indicate that the entire duration will be 180 days?

Option A

You should configure five summary tasks each with a duration of 36 days.

Option B

You should set the Status Date to 180 days into the future.

Option C

You should enter the project timescale in the project calendar.

Option D

You should create a single summary task with the manually scheduled option.

Correct Answer C
Explanation


Question ID 10862

You work as a Project Manager at ABC.com. You are using Microsoft Project Professional 2010 to
manage a new project.
The resources in the project work from 6pm to 10pm four days a week from Monday through
Thursday.
You have been instructed to create a new default calendar for the project so that the working
hours of the part-time resources are reflected.Which of the following actions should you take?

Option A

You should modify the Standard calendar then select the Update Project option.

Option B

You should navigate to the Change Working Time window and click Create New Calendar.
Then change the calendar type in the Project Options dialog box.

Option C

You should change the calendar type to part-time in the Project Options dialog box.

Option D

You should navigate to the Change Working Time window and change the calendar type to
part-time.

Correct Answer B
Explanation