Question ID 10861 | You work as a Project Manager at ABC.com. You are using Microsoft Project Professional 2010 to |
Option A | You should configure five summary tasks each with a duration of 36 days. |
Option B | You should set the Status Date to 180 days into the future. |
Option C | You should enter the project timescale in the project calendar. |
Option D | You should create a single summary task with the manually scheduled option. |
Correct Answer | C |
Question ID 10862 | You work as a Project Manager at ABC.com. You are using Microsoft Project Professional 2010 to |
Option A | You should modify the Standard calendar then select the Update Project option. |
Option B | You should navigate to the Change Working Time window and click Create New Calendar. |
Option C | You should change the calendar type to part-time in the Project Options dialog box. |
Option D | You should navigate to the Change Working Time window and change the calendar type to |
Correct Answer | B |