READ Free Dumps For Microsoft- 70-178
Question ID 10871 | You work as a Project Manager at ABC.com. You are using Microsoft Office Project Professional |
Option A | The duration of the Software Coding task has taken 2 days more than forecast. |
Option B | The duration of the Software Coding task has taken 2 days less than forecast. |
Option C | The Software Coding task is 2 days late. |
Option D | The Software Coding task is 2 days early. |
Correct Answer | C |
Question ID 10872 | You work as a Project Manager at ABC.com. You are using Microsoft Project Professional 2010 to |
Option A | You should view the resource calendar in the Task Inspector utility. |
Option B | You should view the project calendar in the Task Inspector utility. |
Option C | You should run the Level Resource utility. |
Option D | You should click Update Project. |
Correct Answer | A |