Question ID 10871

You work as a Project Manager at ABC.com. You are using Microsoft Office Project Professional
2010 to manage a project to development a new Customer Relationship Management for a
customer.
The Scope, Requirements and Design phases of the project are now complete. The project is now
in the Development phase. One of the tasks in Development phase is named Software Coding
and has just been completed.
The Software Coding task has a finish variance of 2 days.
Which of the following statements describe the Software Coding task?

Option A

The duration of the Software Coding task has taken 2 days more than forecast.

Option B

The duration of the Software Coding task has taken 2 days less than forecast.

Option C

The Software Coding task is 2 days late.

Option D

The Software Coding task is 2 days early.

Correct Answer C
Explanation


Question ID 10872

You work as a Project Manager at ABC.com. You are using Microsoft Project Professional 2010 to
manage a project to development a new software system for a customer.
You enter a manually scheduled task named System Requirements Definition and enter a finish
date for the task of 20th July.You assign a resource named Clive Allen to the System Requirements Definition task. You
discover that the properties of the task have changed. The finish date has now changed to 27th
July and the task mode has changed to automatically scheduled.
What should you do to identify the cause of the changes?

Option A

You should view the resource calendar in the Task Inspector utility.

Option B

You should view the project calendar in the Task Inspector utility.

Option C

You should run the Level Resource utility.

Option D

You should click Update Project.

Correct Answer A
Explanation