READ Free Dumps For Microsoft- 70-178





Question ID 10875

You work as a Project Manager at ABC.com. You are using Microsoft Project Professional 2010 to
manage a project.
The project schedule includes multiple independent networks of tasks with dependencies. You are
viewing the default Gantt chart.
How can you configure the view to display the critical tasks of all the networks of tasks with the
project?

Option A

By selecting the Show Warnings option in the Inspect task utility.

Option B

By selecting the Calculate multiple critical paths check box in the Project 2010 options.

Option C

By selecting Critical from the Filter drop-down box on the View tab.

Option D

By selecting Critical from the Group drop-down box on the View tab.

Correct Answer C
Explanation


Question ID 10876

You work as a Project Manager at ABC.com. You are using Microsoft Project Professional 2010 to
create a project plan.
The project plan must be suitable for project resources who work different hours and different
days. Some resources work Monday to Friday 8 hours a day. Some resources work 4 hours in the evenings from Monday to Friday. Some resources work 12 hour shifts at the weekends.
What should you include in your project plan?

Option A

You should include a summary task for each shift.

Option B

You should include a timeline for each shift.

Option C

You should include a base calendar for each shift.

Option D

You should create a resource pool for each shift.

Correct Answer C
Explanation