Question ID 10875 | You work as a Project Manager at ABC.com. You are using Microsoft Project Professional 2010 to |
Option A | By selecting the Show Warnings option in the Inspect task utility. |
Option B | By selecting the Calculate multiple critical paths check box in the Project 2010 options. |
Option C | By selecting Critical from the Filter drop-down box on the View tab. |
Option D | By selecting Critical from the Group drop-down box on the View tab. |
Correct Answer | C |
Question ID 10876 | You work as a Project Manager at ABC.com. You are using Microsoft Project Professional 2010 to |
Option A | You should include a summary task for each shift. |
Option B | You should include a timeline for each shift. |
Option C | You should include a base calendar for each shift. |
Option D | You should create a resource pool for each shift. |
Correct Answer | C |