Question ID 10867

You work as a Project Manager at ABC.com. You are using Microsoft Project Professional 2010 to
manage a project.
You have added three subtasks named Drawings, Prototype and Review to a summary task
named Design. You want the ability to monitor and compare the actual progress of the tasks to the
original projected schedules. To this end, you have created a number of baselines for the tasks.
Which three of the following steps should you take to update Baseline1 for the three subtasks
only?

Option A

Highlight the Drawings, Prototype and Review subtasks.

Option B

Highlight the Design summary task.

Option C

Click Set Baseline and select Baseline1.

Option D

Select the Selected Tasks radio button.

Option E

Select the Entire Project radio button.

Option F

Select the To all summary tasks checkbox.

Correct Answer A,C,D
Explanation


Question ID 10868

You work as a Project Manager at ABC.com. You are using Microsoft Project Professional 2010 to
manage a project.You are in the process of viewing the Gantt chart for the project. You would, however, like to only
view the tasks on the critical path of the project.
Which of the following actions should you take?

Option A

You should consider choosing Critical from the Highlight Filter drop-down box on the View tab.

Option B

You should consider choosing Critical from the Filter drop-down box on the View tab

Option C

You should consider choosing Critical from the Group drop-down box on the View tab.

Option D

You should consider choosing the Critical Tasks checkbox on the Format tab.

Correct Answer B
Explanation