Question ID 7359 | How does Agile bring predictability to the Planning process? |
Option A | . By allowing the customers to review the progress often |
Option B | . By assigning most of the responsibility to the Product Owner. |
Option C | By making the team self-organized and self-planning |
Option D | . By providing early visibility into the team's progress |
Correct Answer | d |
Question ID 7360 | How should 'done' be defined when multiple teams are working on a single product? |
Option A | All teams must have the same definition of 'done'. |
Option B | . Each team must define and use their own definition of 'done'. |
Option C | The Scrum Master defines when the item is 'done'. |
Correct Answer | a |