Question ID 7355 | In a Scrum project, when would a requirement get added to the Product backlog? |
Option A | When it is developed, but cannot yet be released |
Option B | When the team works on it for a particular release |
Option C | When the customer requests a new requirement. |
Correct Answer | c |
Question ID 7356 | What is the objective of the Scrum-of-Scrums meeting? |
Option A | To inform management about the progress of the project |
Option B | Bring together all team members of all teams |
Option C | Coordinate the work of multiple Scrum teams |
Option D | Kick-off an international Scrum projec |
Correct Answer | c |