Question ID 7349

Sprint planning should result in a commitment on what will be delivered at the end of the Sprint. Who makes this commitment?

Option A

The Product Owner

Option B

The Scrum Master

Option C

The team

Correct Answer c
Explanation


Question ID 7350

A team is estimating story points. They estimate that the story falls between a large (13) and a medium (5) and they assign a story point of 8. What is this technique called?

Option A

Affinity estimation

Option B

Fibonacci estimation

Option C

Triangulation

Correct Answer c
Explanation