READ Free Dumps For Exin- ASF
Question ID 7386 | Which of the following statements best expresses the role that the daily stand-up meeting plays in the monitoring of a Scrum project? |
Option A | The stand-up meeting helps the Scrum Master to update the burn-down chart. |
Option B | The stand-up meeting gives the team insight into their progress and their issues |
Option C | The stand-up meeting lets the Product Owner review the progress of the team. |
Correct Answer | b |
Question ID 7387 | What is the relationship between the Product Backlog, the Release Backlog and the Sprint Backlog?
|
Option A | The Product Backlog is a subset of the Sprint Backlog, which is a subset of the Release Backlog |
Option B | The Release Backlog is a subset of the Product Backlog, which is a subset of the Sprint Backlog |
Option C | The Sprint Backlog is a subset of the Product Backlog, which is a subset of the Release Backlog |
Correct Answer | C |