Question ID 7384 | What must a team do to finish the Product Backlog Item it selects? |
Option A | As much as can be done in the Sprint before the deadline |
Option B | As much as is required to satisfy the definition of 'done'. |
Option C | Analyze, design, program, test and document the PBI. |
Correct Answer | b |
Question ID 7385 | What is the best approach to the transformation? |
Option A | Get a senior executive to champion the transformation |
Option B | Get the team managers to monitor their team's progress on a daily basis. |
Option C | Make a swift transition and start using Scrum for all projects |
Correct Answer | a |