AllExam Dumps

DUMPS, FREE DUMPS, VCP5 DUMPS| VMWARE DUMPS, VCP DUMPS, VCP4 DUMPS, VCAP DUMPS, VCDX DUMPS, CISCO DUMPS, CCNA, CCNA DUMPS, CCNP DUMPS, CCIE DUMPS, ITIL, EXIN DUMPS,


READ Free Dumps For Exin- ASF





Question ID 7374

A 200 member project team is working on a large and complex system with multiple sub- systems. They would like to start using the Agile Scrum methodology. As a Scrum Master, what would your best advice be?

Option A

Scrum is not suited for such a large project. The team should clearly use the Waterfall method or the Crystal Clear method.

Option B

Ask all potential members of the project team to have a meeting first and decide if they agree to use Scrum.

Option C

Agree a logical sub-division of the system so that smaller Scrum teams can work on sub- systems and can add tangible value.

Correct Answer c
Explanation


Question ID 7375

A team estimates a Story using the Planning Poker technique. The team decides to allocate five Story points to the Story, because the Developers estimated two points and the Testers estimated three points. Which statement is true regarding this scenario?

Option A

Points are assigned by the Scrum Master, not by the team.

Option B

Points are assigned for the overall Story, not for parts of the Story

Option C

Points are never estimated, but always determined beforehand

Option D

The team forgets to ask the Product Owner about the estimate.

Correct Answer b
Explanation

Send email to admin@getfreedumps for new dumps request!!!