Question ID 7369 | Who knows most about the progress towards a business objective or a release? |
Option A | The Product Owner |
Option B | The Scrum Master |
Option C | The team |
Correct Answer | a |
Question ID 7371 | A story was estimated at eight ideal hours. A working day is eight hours. Developers can get about six hours of work done on a daily basis. What is the elapsed time required to complete the story? |
Option A | 1.25 days |
Option B | 1.33 days |
Option C | 2 days |
Option D | This cannot be determined without knowing the velocity. |
Correct Answer | b |