Question ID 16955

Which program element should be implemented FIRST in asset classification and control?

Option A

Risk assessment

Option B

Classification

Option C

Valuation 

Option D

Risk mitigation

Correct Answer C
Explanation Explanation: Valuation is performed first to identify and understand the assets needing protection. Risk assessment is performed to identify and quantify threats to information assets that are selected by the first step, valuation. Classification and risk mitigation are steps following valuation.


Question ID 16956

Risk assessment should be built into which of the following systems development phases
to ensure that risks are addressed in a development project?

Option A

Programming

Option B

 Specification

Option C

User testing

Option D

Feasibility

Correct Answer D
Explanation Explanation: Risk should be addressed as early as possible in the development cycle. The feasibility study should include risk assessment so that the cost of controls can be estimated before the project proceeds. Risk should also be considered in the specification phase where the controls are designed, but this would still be based on the assessment carried out in the feasibility study. Assessment would not be relevant in choice A or C.