Question ID 11596 | Which phase of the ADM is an on-going activity that is visited throughout a TOGAF architecture project? |
Option A | Architecture Change Management |
Option B | Implementation governance |
Option C | Migration planning |
Option D | Preliminary Phase |
Option E | Requirements Management |
Correct Answer | E |
Question ID 11597 | Which of the following statements best describes risk management in the ADM? |
Option A | . Risk analysis is best conducted in the Architecture Vision phase so that the risk is eliminated in subsequent phases |
Option B | Risk analysis should be carried out first in the Migration Planning phase |
Option C | Risk analysis is outside the scope of enterprise architecture projects |
Option D | Risk is pervasive in all enterprise architecture activity and should be managed in all phases of the ADM |
Option E | The only risks that are within the scope of enterprise architecture are technological risks |
Correct Answer | D |