READ Free Dumps For The Open Group- OG0-091





Question ID 11561

Complete the sentence. A server consolidation project that does not change the operating characteristics of the applications would require _____.

Option A

a complete ADM cycle

Option B

a complete re-architecting change

Option C

a full revision of the enterprise architecture

Option D

an incremental change

Option E

a simplification change

Correct Answer E
Explanation


Question ID 11562

Which one of the following is an objective of the Preliminary Phase of the ADM?

Option A

To define, scope and prioritize architecture tasks

Option B

To define the architecture principles

Option C

To develop a Target Business Architecture

Option D

To obtain management commitment for this cycle of the ADM

Option E

To prioritize work packages

Correct Answer B
Explanation