Question ID 10917

You work as the network administrator at ABC.com. Your responsibilities include maintaining the
Project Server 2010 environment.
The Project Server 2010 environment consists of the following two servers. A Windows Server
2008 R2 server named ABC-SQL1 runs SQL Server 2008 R2. A Windows Server 2008 R2 server
named ABC-SPS1 runs SharePoint Server 2010 and Project Server 2010.
You are configuring a new laptop for a user named Mia Hamm. Mia will be working on an existing
project. You install Project Professional 2010 and configure Mia’s user permissions on ABC-SPS1
to allow her to edit projects using Project Professional.
What should you do to enable Mia to open the project?

Option A

You should run Project Professional on Mia’s laptop, select the Open Project option and enter
the URL for ABC-SPS1.

Option B

You should run Project Professional on Mia’s laptop and configure the account settings for
ABC-SPS1.

Option C

You should run Project Server on ABC-SPS1 and open the project.

Option D

You should create an account for Mia using SharePoint Central Administration.

Correct Answer B
Explanation


Question ID 10918

You work as the network administrator at ABC.com. You are in the process of configuring a
Project Server 2010 environment.
The network includes the following two Exchange servers:
ABC-Exch1 runs Exchange Server 2007 R2 and is configured to run the Client Access Server role.
ABC-Exch2 runs Exchange Server 2007 R2 and is configured to run the Mailbox Server role.
You need to configure Project Server 2010 to integrate with the ABC.com Exchange environment.
You have configured the following two servers:
ABC-SQL1 runs SQL Server 2008 R2.
ABC-SPS1 runs SharePoint Server 2010 and Project Server 2010.
You plan to enable task synchronization in Project Web App (PWA).
What should you do first?

Option A

You should create a user account for ABC-Exch1 in Project Web App (PWA).

Option B

You should create a user account for ABC-Exch2 in Project Web App (PWA).

Option C

You should add the computer account for ABC-SPS1 to the Exchange Domain Servers group
in Active Directory.

Option D

You should add the Farm Administrator’s user account to the local Administrators group on
ABC-Exch1.

Option E

You should add the Farm Administrator’s user account to the local Administrators group on
ABC-Exch2.

Correct Answer A