READ Free Dumps For Microsoft- 70-177
Question ID 10954 | You work as a Project Manager at ABC.com. You manage projects using Project Server 2010. |
Option A | You should save the project plan with a different name. |
Option B | You should restart the workflow before modifying the project plan. |
Option C | You should checkout the project plan. |
Option D | You should force a check in of the project plan. |
Correct Answer | D |
Question ID 10955 | You work as the network administrator at ABC.com. Your responsibilities include maintaining the |
Option A | You should add the board members to the category. |
Option B | You should add the non-board members to the category. |
Option C | You should set all category permissions to Deny. |
Option D | You should set all category permissions to Deny. |
Correct Answer | B,C |