Question ID 10929

You work as a Project Manager at ABC.com. You are using the Project Server 2010 environment
to manage a complex project.
You discover that you do not always receive timesheet updates submitted by other members of
the project team.
You have been tasked with making sure that you always receive all timesheet updates submitted
by everyone in the project team.
Which of the following actions should you take?

Option A

You should configure the timesheets settings to enable Single Entry Mode (SEM).

Option B

You should configure the timesheets settings to disable Single Entry Mode (SEM).

Option C

You should modify the timesheets using the Adjust Timesheet option.

Option D

You should modify the administrative time category settings in Time and Task Management.

Correct Answer A
Explanation


Question ID 10931

You work as a Project Manager at ABC.com. You are managing a project using Project Server
2010.
You have been instructed to create a Project Server resource for the purpose of tracking the
number of bricks used in a new ABC.com housing development.
Which of the following actions should you take?

Option A

You should create a cost resource.

Option B

You should create a material resource.

Option C

You should create a people resource.

Option D

You should create an equipment resource.

Option E

You should create a generic resource.

Correct Answer B
Explanation