Question ID 3335 | During the RFQ lifecycle, the RFQ is assigned certain statuses. Identify the RFQ lifecycle and its correct sequence. |
Option A | A. In Process, Active, Printed, Closed |
Option B | B. Active, Printed, Accepted, Complete |
Option C | C. Active, In Process, Received, Complete |
Option D | D. In Process, Received, Accepted, Closed |
Option E | E. Requested, Printed, In Process, Received |
Correct Answer | A |
Question ID 3336 | BMC is preparing to convert purchase orders (POs) from their legacy system into Oracle. |
Option A | A. Leave the setups as is, but convert the legacy POs first, then the manual POs. |
Option B | B. The system is set up for nonintelligent numbering; therefore, the legacy POs cannot be converted with intelligent numbering. |
Option C | C. No setup changes are necessary as long as you ensure that the next automatic number is |
Option D | D. Switch setups from Automatic to Manual, then enter the manual POs, and then switch setups back to Automatic and automatically convert all legacy POs. |
Option E | E. Enter the manual POs, then change the PO numbering options to Manual (alphanumeric), convert legacy POs, and then change the PO numbering options back to Automatic. |
Correct Answer | E |