Question ID 20912

Which of the following statements about the Project Initiation Documentation are true?
1. The Project Initiation Documentation is used to ensure that a sound basis exists before the Project Board authorizes a project.
2. The Project Initiation Documentation should be updated at the end of each stage to reflect the current status of a project.

Option A

Only 1 is true

Option B

Only 2 is true

Option C

Both 1 and 2 are true

Option D

Neither 1 or 2 are true

Correct Answer C
Explanation


Question ID 20913

Which is an objective of the Initiating a Project process?

Option A

Develop the corporate quality management system as part of the Project Initiation Documentation

Option B

Prepare the plans for the subsequent stages

Option C

Summarize how the organization's project management method will be tailored for the project

Option D

Request authority from corporate management to deliver the project

Correct Answer C
Explanation